Leamington Spa – The Royal Spa Centre

The Royal Spa Centre, 2017

The Royal Spa Centre in Leamington Spa, owned and operated by Warwick District Council, has made a significant investment in a new automated stage rigging system and new stage lighting dimmers for its provincial theatre.

Glantre was engaged as Principle Contractor by Warwick Council to perform the complete strip out of the of existing over stage machines, dimmers, ageing and non-compliant dimmer circuit wiring, containment and incoming power distribution. new systems to replace those stripped out was to comprise of:

  • 29 ASM HWCA Junior BGV-C1 certified hoists, 500
    kg WLL, 0.4m/s on 200mm centres
  • SIL-3 Certified control system with advanced touch panel control console
  • New head pulleys and loft blocks to suit the new installation
  • New wire ropes and ladder bars
  • New hoist power / control cable infrastructure and containment
  • New main technical power distribution board
  • 9 x Zer088 Chill Pro24 dimmer racks providing 216 channels with by-pass switching, including new dimmer circuit cabling and containment and new lighting control and Ethernet cable infrastructure

The ASM HWCA Junior hoists selected by Glantre for this project are certified to the BGV-C1 standard. BGV-C1 is the highest certification level of a stringent standard, developed in Germany, that sets out a set of requirements for staging and production facilities. The standard deals with every aspect of staging a production, and brings together various DIN standards pertaining to each aspect of the technical systems employed. There are three levels within the standard: D8, D8+ and C1. Lifting machinery can be employed in certain scenarios depending on its level of compliance. For example, machines that are compliant to D8 standard can only be used for static suspension of loads above people when independently secured with a safety bond; machinery compliant to D8+ standards can be used to suspend static loads above people without an independent safety bond, movement of loads above people remains prohibited; machinery compliant to C1 standards can be used to move its load above people.

The control system itself is both intuitive and fully featured. The architecture is straightforward and consists of the hoist power pack, LC-8 hoist controllers and the control desk. The hoist power packs connect via radial links to an LC-8 controller (8 hoists per LC-8). The technical team can control from two positions, both on the fly gallery or the Stage management position, stage left.